Disruption claims and loss of productivity

Disruption is loss of productivity: the work took more labour and plant hours than it should have, because the conditions it was carried out in were changed. A disruption claim has to show the loss, its cause and its cost, from the project’s own records.

What disruption is

Work is disrupted when something disturbs, hinders or interrupts the contractor’s normal way of working, so that the same output takes more hours. Access given piecemeal, work forced out of sequence, late or changed design, and trades stacked on top of one another are common causes.

Disruption is not delay. Delay is about time: the works finished late. Disruption is about productivity: the work cost more to do, whether or not it finished late. The two are analysed separately.

What a claim has to show

  • Which work was affected, where and when.
  • What caused the loss of productivity, and that the cause is one for which the other party is responsible under the contract.
  • How much productivity was lost, measured from the records.
  • What the lost productivity cost.

Low productivity has other causes as well: poor supervision or planning, rework, weak coordination of subcontractors, or a tender that was too optimistic. These have to be taken out. Disruption is not simply the difference between what was planned and what happened.

How lost productivity is measured

The Society of Construction Law Delay and Disruption Protocol (2nd edition, February 2017) groups the methods in two families.

  • Productivity-based methods measure the lost productivity and then price it. They include studies of the project itself (measured mile, earned value, programme analysis, work or trade sampling and system dynamics modelling), comparisons with similar projects, and industry studies.
  • Cost-based methods compare planned and actual labour or cost directly, without first measuring productivity.

The Protocol ranks studies of the project itself above comparisons with other projects, and those above industry studies. It states a preference for the measured mile where the records allow it and the analysis is properly carried out.

The Protocol is published guidance, not a contract document and not a statement of the law. It was written with English law in mind and gives way to the contract and the governing law. Where this page says what the Protocol recommends, that is a summary of the Protocol, not an opinion on any dispute.

The measured mile

A measured mile analysis compares output on a stretch of work that was not disrupted with output on the same kind of work that was, on the same project. Because both come from the same job, the comparison leaves out much of what makes one project differ from another. It depends on records that show hours and output by area and by activity.

The records we ask for

  • Labour allocation records: who worked where, on what, for how many hours.
  • Progress records: quantities installed, by area and by period.
  • Plant records and returns.
  • The tender build-up and the planned outputs.
  • The programme and its updates.
  • Instructions, drawing revisions, access records and correspondence that show the events relied on.

Experience

  • An interim disruption claim valued by measured mile for a contractor on gas export pipelines in Saudi Arabia.
  • Disruption and productivity loss among the issues in an expert procedure and arbitration on phosphate processing facilities in North Africa.
  • Disruption across MEP packages in a DIAC arbitration on a landmark hotel in the UAE.

Related experience

QuantumDelay

Phosphate processing facilities

Region
North Africa
Forum
Pre-arbitral expert procedure (ICC expert determination), then arbitration
Parties
Employer, contractor, subcontractor
Our role

Lead quantum expert; delay expert advice; quantum analysis

Issues

Prolongation, disruption and productivity loss, head office overheads, variations, subcontractor claims

Evidence

Written and oral testimony in the expert procedure; the arbitration settled before the hearing

DelayQuantum

Landmark hotel

Region
UAE
Forum
DIAC arbitration
Parties
Subcontractor v main contractor (MEP packages)
Our role

Delay expert; quantum expert; quantum analysis support

Issues

Responsibility for delay; variations, prolongation and disruption across MEP packages; alleged scope creep

Evidence

Expert reports and a joint statement

Quantum

Slaughterhouse and associated infrastructure

Region
Gulf
Forum
Arbitration
Parties
Main contractor v employer
Our role

Quantum expert; quantum analysis support

Issues

Prolongation, disruption, variations, head office overheads, late payment

Evidence

Expert report

Questions and answers

What is a disruption claim?

A claim for the extra cost of work that took more labour or plant than it should have because the conditions of working were changed by events for which the other party is responsible.

What is the difference between delay and disruption?

Delay is about time: the works finished later than they should have. Disruption is about productivity: the work took more effort than it should have. A job can be disrupted without being delayed.

What is a measured mile analysis?

A way of measuring lost productivity. It compares output on a stretch of work that was not disrupted with output on the same kind of work that was, using the project’s own labour and progress records.

What if no part of the work was free of disruption?

The Society of Construction Law Protocol describes other methods, including earned value analysis, comparison with similar projects, industry studies and cost-based methods. It treats them as less reliable than a study of the project’s own productivity, and what can be done depends on the records.

What records does a disruption claim need?

Records made at the time that show hours and output by area and by activity: labour allocation sheets, progress quantities, plant records, the programme and its updates, and the instructions and correspondence that show the events relied on.

Can planned hours simply be compared with actual hours?

On its own that comparison shows an overrun, not its cause. The Protocol describes cost-based methods of this kind and treats them as less reliable than measuring productivity on the project, because the tender may have been wrong and other causes may be included.