Landmark hotel
Delay expert; quantum expert; quantum analysis support
Responsibility for delay; variations, prolongation and disruption across MEP packages; alleged scope creep
Expert reports and a joint statement
The final account is the last statement of what is due under a construction contract. It gathers every item of value and every deduction into one figure, so every disagreement on the project ends up in it.
For every item we ask the same four questions. Was the cost or loss actually incurred? Was it caused by the event relied on? Is it valued the way the contract requires? Has any of it been counted twice?
Where the parties’ figures cannot be reconciled, the account is rebuilt from first principles: from the contract, the drawings and instructions, the measured quantities and the cost records. Where the parties disagree on the facts, the report gives a figure on each side’s case, and it says plainly where the records do not support a figure.
An independent review of a final account, before it is submitted or before a response is given, shows which items stand up and which do not. That is advisory work, done in the client’s interest, and it is kept apart from our work as experts. More is on our claim review and advisory page.
Delay expert; quantum expert; quantum analysis support
Responsibility for delay; variations, prolongation and disruption across MEP packages; alleged scope creep
Expert reports and a joint statement
Quantum expert
Contract balance, retention, additional man-hours, performance bonds, liquidated damages, non-compliant work, defects
Expert report
Quantum expert; quantum analysis support
Prolongation, disruption, variations, head office overheads, late payment
Expert report
The last statement of the sum due under a construction contract, after all the work, variations, claims, deductions and payments have been taken into account.
Because every unresolved item on the project lands in them: variations that were never agreed, quantities that were never measured, claims for delay and disruption, and deductions for defects and late completion.
Values each item independently on the contract and the records, gives a figure on each party’s case where the facts are disputed, and says plainly where a figure is not supported by the records.
The account is rebuilt from the records that do exist: the contract, the drawings and instructions, measured quantities and cost records. The report states every assumption and every figure the records do not support.
Yes. Our experience includes a DIAC arbitration between an MEP subcontractor and a main contractor on a landmark hotel in the UAE, on variations, prolongation and disruption across the MEP packages.
Yes. An independent review before submission shows which items the records support and where the gaps are, while there is still time to fill them.
Michael RoosFounding Partner, Testifying Quantum Expert
+971 (0)55 869 5337Jamie ShaftoFounding Partner, Testifying Delay Expert
+971 (0)58 569 3416Stephen M JohnPartner, Testifying Technical Expert
+44 (0)7891 784 891Michael WhitingPartner, Quantum Expert
+44 (0)7762 124 220