Glossary of construction dispute terms
Plain definitions of the terms used in construction claims and disputes. Each one links to the page that covers the subject.
These are general explanations. What a term means in a dispute depends on the contract and the governing law, and that is a question for your lawyers.
A
Acceleration
Carrying out work faster than planned, with more resources or a changed sequence, to finish earlier or to recover delay. See Extension of time claims.
Adjudication
A fast procedure in which an independent adjudicator decides a dispute, usually within weeks. The decision binds the parties unless and until the dispute is finally decided in arbitration or in court. See Expert witness services.
Arbitration
A private process in which the parties agree that one or more arbitrators, in place of the courts, will decide their dispute in a binding award. See Expert witness services.
As-built programme
A record, set out as a programme, of when each part of the works was actually carried out. See Forensic delay analysis.
As-planned versus as-built windows analysis
A method of delay analysis that divides the job into windows and, in each, compares planned dates with actual dates along the critical path. See Forensic delay analysis.
B
Back-to-back
A subcontract written so that its terms follow those of the main contract, including the terms on payment, claims and time. See Payment disputes.
Baseline programme
The programme that shows how the contractor planned to carry out the works at the start. Progress and delay are measured against it. See Forensic delay analysis.
BCDR
The Bahrain Chamber for Dispute Resolution, an arbitration and mediation centre in Manama, Bahrain. See Construction expert witnesses in the UAE.
C
Claims consultant
An adviser who prepares, reviews or defends construction claims in the client’s interest. Different from an expert witness, whose duty is to the tribunal. See Claims consultant or expert witness.
Collapsed as-built analysis
A method of delay analysis that takes the delay events out of a logic-linked as-built programme to show when the works would have finished without them. See Forensic delay analysis.
Compensable delay
Delay for which the contractor is entitled to money as well as time. See Prolongation costs.
Concurrent delay
Delay to completion caused by two events at once, one at the employer’s risk and one at the contractor’s, where each is an effective cause of the delay. See Concurrent delay.
Constructive acceleration
Acceleration a contractor carries out to meet the existing completion date because an extension of time it says was due was not granted. Whether the cost can be recovered depends on the contract and the governing law. See Extension of time claims.
Contemporaneous records
Records made at the time of the events they describe, such as site diaries, progress reports, minutes, notices and correspondence. See Forensic delay analysis.
Contra charge
A sum one party deducts from what it owes the other, for example for the cost of putting right defective work. See Final account disputes.
Critical delay
Delay to an activity on the critical path, which therefore delays completion. See Forensic delay analysis.
Critical path
The longest chain of activities through a programme. It fixes the earliest date on which the works can be completed, so delay to an activity on it delays completion. See Forensic delay analysis.
Critical path method (CPM)
A way of planning in which activities are linked by logic, so that the critical path and the float on every activity can be calculated. See Forensic delay analysis.
Culpable delay
Delay for which the contractor is responsible under the contract. See Concurrent delay.
D
Dayworks
Work valued on the time and materials actually spent, at rates set in the contract, where it cannot fairly be valued by measurement. See Final account disputes.
Decennial liability
A rule in the civil codes of several Gulf states under which the contractor and the designer are liable for ten years for the collapse of a building and for defects that threaten its stability or safety. See Construction defects.
Defect
Work or design that does not meet what the contract required. See Construction defects.
Defects liability period
A period after completion during which the contractor must return to put right defects that appear. Some contracts call it the defects notification period. See Construction defects.
Delay analysis
The study of what delayed a project and by how long, using the programmes and the progress records. See Forensic delay analysis.
Delay damages
A sum fixed in the contract that the contractor pays for each day or week by which completion is late. Also called liquidated damages. See Extension of time claims.
Delay expert
An expert witness who gives an independent opinion on what delayed completion and by how long. See Delay expert witness.
DIAC
The Dubai International Arbitration Centre, which administers arbitrations under its own rules. See Construction expert witnesses in the UAE.
Dispute board
A panel of one or three people named under the contract to help the parties avoid disputes and to decide them when they arise. The FIDIC forms call it the DAB or the DAAB. See Expert determination.
Disruption
Disturbance, hindrance or interruption to a contractor’s normal working methods that results in lower productivity. See Disruption claims.
E
Earned value analysis
A way of measuring productivity that compares the hours or cost planned for the work actually done with the hours or cost actually spent on it. See Disruption claims.
Eichleay formula
A formula from the United States for estimating unabsorbed head office overheads in a period of delay, based on the contract’s share of the contractor’s total billings. See Prolongation costs.
Emden formula
A formula for estimating head office overheads and profit in a period of delay, using the percentage for overheads and profit taken from the contractor’s accounts. See Prolongation costs.
Employer risk event
An event that the contract places at the employer’s risk as to time, money or both. The term is used in the Society of Construction Law Protocol. See Extension of time claims.
Engineer’s determination
Under FIDIC forms of contract, the engineer’s decision on a claim for time or money where the parties have not agreed it. See Extension of time claims.
EOT
Short for extension of time. See Extension of time claims.
Excusable delay
Delay for which the contractor is entitled to an extension of time. It may or may not carry money. See Extension of time claims.
Expert determination
A process in which the parties appoint an independent expert to decide a technical or valuation question, on the terms their contract or agreement sets. See Expert determination.
Expert witness
A person with specialist knowledge who gives an independent opinion to a tribunal or court. The expert’s duty is to the tribunal, not to the party who pays. See Expert witness services.
Extension of time
A change to the contract completion date, made under the contract, when the works are delayed by an event for which the employer carries the risk. See Extension of time claims.
F
FIDIC
The International Federation of Consulting Engineers. It publishes standard forms of contract used on international construction and engineering projects. See Dispute resolution.
Final account
The last statement of the sum due under a construction contract, after all the work, variations, claims, deductions and payments have been taken into account. See Final account disputes.
Float
The time by which an activity can be delayed before it delays completion (total float) or the start of the next activity (free float). See Extension of time claims.
Forensic delay analysis
Delay analysis carried out after the event, as evidence in a claim or a dispute. See Forensic delay analysis.
G
GCC
The Gulf Cooperation Council. Its six member states are Bahrain, Kuwait, Oman, Qatar, Saudi Arabia and the United Arab Emirates. See Construction expert witnesses in the UAE.
Global claim
A claim in which one total loss is attributed to several causes together, without showing the loss that each caused. See Final account disputes.
H
Head office overheads
The cost of running the contractor’s business as a whole, such as head office staff and premises, as distinct from the cost of running a site. See Prolongation costs.
Hudson formula
A formula for estimating head office overheads and profit in a period of delay, using the percentage for overheads and profit in the tender. The Society of Construction Law Protocol does not support its use. See Prolongation costs.
I
ICC
The International Chamber of Commerce. Its International Court of Arbitration administers arbitrations under the ICC Rules. See Expert witness services.
Impacted as-planned analysis
A method of delay analysis that adds the delay events to the original programme and recalculates it. It takes no account of actual progress. See Forensic delay analysis.
J
Joint statement
A document in which the experts on each side record, after meeting, what they agree on, what they disagree on and why. See Expert witness services.
K
KCAC
The Kuwait Commercial Arbitration Centre, the arbitration centre of the Kuwait Chamber of Commerce and Industry. See Construction expert witnesses in the UAE.
L
LCIA
The London Court of International Arbitration, an arbitration institution based in London that administers arbitrations under its own rules. The DIFC-LCIA Arbitration Centre in Dubai, which was linked to it, was abolished by Dubai Decree No. 34 of 2021. See Construction expert witnesses in the UAE.
Liquidated damages
A sum fixed in the contract in advance as payable for a breach. In construction it usually means delay damages. See Extension of time claims.
Loss of productivity
More labour or plant hours spent for the same output. It is what a disruption claim measures. See Disruption claims.
M
Measured mile
A way of measuring lost productivity that compares output on work that was not disrupted with output on the same kind of work that was, on the same project. See Disruption claims.
Mitigation
The steps a party is expected to take to reduce delay or loss. What is required depends on the contract and the governing law. See Extension of time claims.
Muqawala
The Arabic name, used in the UAE Civil Transactions Law and other Gulf civil codes, for a contract to make something or carry out work, which includes a construction contract. See Construction expert witnesses in the UAE.
N
Notice of claim
The written notice a contract requires a party to give, within a stated time, when an event occurs that may entitle it to time or money. See Extension of time claims.
P
Party-appointed expert
An expert witness instructed by one party to a dispute. The duty is still to the tribunal. See Independence and expert duties.
Pay when paid
A subcontract term that makes payment to the subcontractor depend on the main contractor being paid first. Whether it can be relied on depends on the contract and the governing law. See Payment disputes.
Preliminaries
The contractor’s costs of running the site that are not tied to one item of work, such as site staff, offices, plant and temporary works. See Prolongation costs.
Prolongation costs
The time-related costs a contractor incurs because it is on a project for longer than planned. See Prolongation costs.
Provisional sum
A sum included in the contract price for work that could not be fully defined at tender. It is adjusted when the work is instructed and valued. See Final account disputes.
Q
QICCA
The Qatar International Center for Conciliation and Arbitration, the local arbitration centre in Doha. See Construction expert witnesses in Qatar.
Quantity surveyor
A construction professional who measures and values building and engineering work, prices changes and agrees accounts. A quantity surveyor who gives evidence on value in a dispute is usually called a quantum expert. See Quantity surveying experts.
Quantum
The amount of money: what a claim, a variation or a loss is worth. See Quantum expert witness.
Quantum expert
An expert witness who gives an independent opinion on the value of claims and counterclaims. See Quantum expert witness.
R
Remeasurement
Valuing the work by measuring the quantities actually carried out and applying the contract rates. See Final account disputes.
Retention
A percentage held back from each payment as security. It is usually released in stages, at completion and at the end of the defects liability period. See Final account disputes.
Retrospective longest path analysis
A method of delay analysis that traces the longest path back from the actual completion date through a detailed as-built programme. See Forensic delay analysis.
S
SCCA
The Saudi Center for Commercial Arbitration, based in Riyadh, which administers arbitrations under its own rules. See Construction expert witnesses in Saudi Arabia.
SCL Protocol
The Society of Construction Law Delay and Disruption Protocol: published guidance on delay and disruption. The second edition is dated February 2017. It is not a contract document. See Forensic delay analysis.
Single joint expert
One expert appointed for both parties to give evidence on an issue, in place of an expert on each side. See Expert witness services.
Structural defect
A defect that affects the strength or stability of a building or structure, as opposed to its finishes or its services. See Construction defects.
T
Technical expert
An expert witness who gives an independent opinion on engineering questions, such as design, construction method and the cause of defects. See Technical expert witness.
Termination account
The statement of what is due between the parties after a construction contract is terminated: the value of the work done, less payments and proper deductions, with the claims each way. See Termination of a construction contract.
Time bar
A contract term under which a claim is said to be lost if notice is not given within a stated time. Whether it has that effect is a legal question. See Extension of time claims.
Time impact analysis
A method of delay analysis that adds each delay event to the programme as it stood when the event arose, to show the likely effect on completion. See Forensic delay analysis.
Time slice windows analysis
A method of delay analysis that uses the programmes updated during the works to find the critical path and the delay in each period, and then the cause. See Forensic delay analysis.
Tribunal
The arbitrator or arbitrators, court, adjudicator or board that decides the dispute. See Independence and expert duties.
Tribunal-appointed expert
An expert appointed by the tribunal or court itself, not by one of the parties. See Expert witness services.
U
Unabsorbed overheads
Head office overheads that a delayed project could not contribute to as planned, because its resources were tied up and could not earn revenue elsewhere. See Prolongation costs.
V
Variation
A change to the works instructed or agreed under the contract: an addition, an omission or a change to design, quality, quantity or sequence. See Variation claims.
W
Windows analysis
Any delay analysis that divides the project into periods, or windows, and examines each in turn. See Forensic delay analysis.
Witness conferencing
A way of taking expert evidence in which the experts on each side give evidence at the same time and are questioned together. Also called concurrent evidence or hot-tubbing. See Expert witness services.