Hospital
Delay expert
Responsibility for delay
Expert reports, joint statements; oral evidence under cross-examination by King’s Counsel
Concurrent delay arises when completion is delayed by two causes at once, one at the employer’s risk and one at the contractor’s. It is one of the most argued points in construction disputes, because it decides who bears the time and who bears the cost.
The Society of Construction Law Delay and Disruption Protocol (2nd edition, February 2017) uses the term in two ways. True concurrent delay is two delay events, one at the employer’s risk and one at the contractor’s, that happen at the same time and whose effects are felt at the same time. The Protocol says this is rare. More often the term is used where the two events arise at different times but their effects are felt at the same time.
In both cases, the Protocol says there is concurrent delay only if each event is an effective cause of delay to completion. An event that happened in the same period but did not affect the critical path does not make the delay concurrent.
Where concurrent delay is established, the Protocol’s position is that the contractor should have an extension of time for the employer’s delay, and that the contractor’s own concurrent delay should not reduce it.
Money is treated differently. Where the two delays are concurrent, the Protocol’s position is that the contractor should recover its extra cost only if it can separate the cost caused by the employer’s delay from the cost caused by its own. Cost that it would have incurred in any event because of its own delay is not recoverable.
A common argument is about an employer’s event that falls in a period when the contractor is already in delay for its own reasons. The Protocol sets out two views. On one, both events are causes of the delay for the period in which they overlap. On the other, the employer’s event causes no delay to completion, because the works were going to be late by a longer period anyway. The Protocol recommends the second view and says that this would need to be looked at again if an appeal court took a different approach.
Many contracts now say expressly how concurrent delay is to be treated, and those terms govern. Where the contract is silent, the answer depends on the governing law. The civil codes of the Gulf states are not the same as English law on causation and on sharing responsibility. Which rule applies in a dispute is a question for the parties’ lawyers and for the tribunal.
The Protocol is published guidance, not a contract document and not a statement of the law. It was written with English law in mind and gives way to the contract and the governing law. Where this page says what the Protocol recommends, that is a summary of the Protocol, not an opinion on any dispute.
Delay expert
Responsibility for delay
Expert reports, joint statements; oral evidence under cross-examination by King’s Counsel
Delay expert
Responsibility for delay
Independent delay analysis and expert reports
Delay to completion caused by two events at once, one at the employer’s risk and one at the contractor’s, where each is an effective cause of the delay.
The contract decides. Where it is silent, the Society of Construction Law Protocol’s position is that the contractor’s own concurrent delay should not reduce the extension of time due for the employer’s delay. The governing law may lead to a different answer.
The Protocol’s position is that it can recover only the extra cost it is able to show was caused by the employer’s delay, and not cost it would have incurred anyway because of its own delay.
The Protocol describes true concurrent delay, where two events occur at the same time and their effects are felt at the same time, as a rare occurrence. Events that arise at different times and overlap in their effects are more common.
That is a legal question for the parties’ lawyers. The Protocol was written with English law in mind. The delay expert’s part is the facts: which events delayed completion, when, and by how long.
Establishes from the programmes and records which events were on the critical path in each period, and reports the delay on each party’s case, so that the tribunal can apply the contract and the law to the facts.
Michael RoosFounding Partner, Testifying Quantum Expert
+971 (0)55 869 5337Jamie ShaftoFounding Partner, Testifying Delay Expert
+971 (0)58 569 3416Stephen M JohnPartner, Testifying Technical Expert
+44 (0)7891 784 891Michael WhitingPartner, Quantum Expert
+44 (0)7762 124 220