Extension of time claims

An extension of time, often shortened to EOT, moves the contract completion date when the works are delayed by something the contract places at the employer’s risk. We prepare and defend extension of time claims as advisers, review them independently, and give delay evidence on them as experts.

What an extension of time does

It helps both parties. The contractor is relieved of damages for delay for the period of the extension and can reprogramme the rest of the works. The employer has a new completion date to plan around and to hold the contractor to. An extension of time is about time. Money is a separate question.

What a claim has to show

  • The event: what happened and when, shown by records made at the time.
  • The risk: that the contract places that event at the employer’s risk.
  • The procedure: that the notices and particulars the contract requires were given.
  • The effect: that the event delayed completion, and by how long. It is not enough that the event happened.

The exact requirements are in the contract. Whether they were met, and what follows if they were not, are legal questions for the tribunal. The delay analysis supplies the facts: which events fell on the critical path and how many days each one cost.

What the Protocol says

The Society of Construction Law Delay and Disruption Protocol (2nd edition, February 2017) sets out principles on extensions of time. In summary:

  • The parties should follow the contract’s requirements on notices, particulars and assessment.
  • Claims should be made and assessed as close in time to the event as possible. Waiting to see what happens is discouraged.
  • An extension is due where the employer’s risk event is predicted to delay completion, which in general means that it affects the critical path.
  • Unless the contract says otherwise, where there is float left in the programme, an extension is due only to the extent that the delay uses up the float on the critical path.
  • An extension of time does not by itself entitle the contractor to money, and money does not depend on an extension.

The Protocol is published guidance, not a contract document and not a statement of the law. It was written with English law in mind and gives way to the contract and the governing law. Where this page says what the Protocol recommends, that is a summary of the Protocol, not an opinion on any dispute.

During the job and after it

A claim made while the works are going on looks forward: what is this event likely to do to the completion date? A claim assessed after completion looks back at what delayed the works. The Protocol notes that a forward-looking analysis may no longer be appropriate once the works are finished or the effect of the event is long past. The methods used to look back are on our forensic delay analysis page.

What we do

  • Prepare extension of time claims for contractors and subcontractors, with the delay analysis and the supporting records.
  • Defend claims for employers, and review the engineer’s or the employer’s determination.
  • Review a claim independently before it is submitted, funded or taken to arbitration.
  • Decide claims as independent determiner where the parties ask for that.
  • Give delay expert evidence in arbitration.

Preparing or defending a claim is advisory work, done in the client’s interest. Giving evidence is expert work, and the duty is to the tribunal. We tell you at the outset which role we are in. We do not act as testifying expert in a dispute in which we have advised the same party, unless that has been disclosed and the tribunal and the parties have had the chance to object.

Experience

  • Consolidated extension of time claims for EPC contractors on power and LPG projects in the UAE.
  • An independent review of a contractor’s delay claims on a gas pipeline, to inform a funding decision.
  • An employer’s defence before a FIDIC dispute board on a 28 km water tunnel in South Asia.
  • Reviews of delay claims and engineer’s determinations for an owner on a commercial district development in Saudi Arabia.

Related experience

DelayQuantumCross-examined by KC

LPG extraction and fractionation plant

Region
Gulf
Forum
ICC arbitration
Parties
EPC contractor v subcontractor (two subcontracts)
Our role

Delay expert; quantum expert for the main contractor

Issues

Responsibility for delay, prolongation, disruption, variations, head office overheads

Evidence

Oral evidence under cross-examination by King’s Counsel (delay)

DelayQuantum

Landmark hotel

Region
UAE
Forum
DIAC arbitration
Parties
Subcontractor v main contractor (MEP packages)
Our role

Delay expert; quantum expert; quantum analysis support

Issues

Responsibility for delay; variations, prolongation and disruption across MEP packages; alleged scope creep

Evidence

Expert reports and a joint statement

Questions and answers

What is an extension of time in a construction contract?

A change to the contract completion date, made under the contract, when the works are delayed by an event for which the employer carries the risk. It relieves the contractor of delay damages for that period and gives the employer a new date for completion.

What does a contractor have to show to get an extension of time?

In general: that the event happened, that the contract places it at the employer’s risk, that the notices the contract requires were given, and that the event delayed completion. The exact requirements are in the contract.

Does an extension of time entitle the contractor to money?

Not automatically. Time and money are assessed separately, each under its own contract terms. The Society of Construction Law Protocol states the same principle: entitlement to an extension of time does not automatically lead to compensation.

Who owns the float in a programme?

The contract decides. Where it is silent, the Protocol’s guidance is that an extension of time is due only to the extent that the employer’s delay uses up the float on the critical path and so delays completion.

What happens if a notice was given late?

That depends on the wording of the contract and the governing law, and is a question for the parties’ lawyers. A delay expert or claims adviser can show from the records what was sent, when, and what it said.

Can the firm that prepares an extension of time claim also give expert evidence on it?

We do not act as testifying expert in a dispute in which we have advised the same party, unless that has been disclosed and the tribunal and the parties have had the chance to object.