Forensic delay analysis

Forensic delay analysis looks back at a project to establish what delayed completion and by how long. It is the evidence that an extension of time claim, a claim for prolongation costs or a defence to delay damages rests on.

What forensic delay analysis is

During a project, a planner looks forward: what will this event do to the completion date? In a dispute, the delay analyst looks back: what did delay completion, and by how many days? The analysis is built from the programmes and the progress records the project produced at the time.

The work turns on the critical path, the chain of activities that fixes the completion date at any point in the job. Only delay on that path delays completion. The critical path can move as the job goes on, so the analysis has to follow it through the works and not assume that it stayed where the first programme put it.

The six methods in common use

The Society of Construction Law Delay and Disruption Protocol (2nd edition, February 2017) describes six methods of delay analysis in common use.

  • Impacted as-planned analysis: the delay events are added to the original programme, which is recalculated to show their effect on the planned completion date. It takes no account of actual progress.
  • Time impact analysis: each delay event is added to the programme as it stood when the event arose, and the programme is recalculated to show the likely effect on completion as it then appeared.
  • Time slice windows analysis: the job is divided into periods, often monthly, using the programmes updated during the works. The critical path and the delay in each period are found first, and the records are then examined for the cause.
  • As-planned versus as-built windows analysis: the job is divided into windows and, in each, planned dates are compared with actual dates along the critical path, which is established from the facts more than from software.
  • Retrospective longest path analysis: a detailed as-built programme is prepared, the longest path is traced back from the actual completion date, and its dates are compared with the planned dates.
  • Collapsed as-built analysis: the delay events are taken out of a logic-linked as-built programme to show when the works would have finished without them.

Some of these start from an event and model its effect. Others start from the delay that occurred and look for its cause. Each has limits, and each needs different records.

The Protocol is published guidance, not a contract document and not a statement of the law. It was written with English law in mind and gives way to the contract and the governing law. Where this page says what the Protocol recommends, that is a summary of the Protocol, not an opinion on any dispute.

How a method is chosen

For an analysis carried out after the event, the second edition of the Protocol does not prefer one method over the others. It lists the matters that should decide the choice:

  • what the contract says;
  • the kind of events in issue;
  • the kind of project;
  • what is proportionate to the value of the project or the dispute;
  • the time available;
  • the records that exist, and their quality;
  • the programmes that exist, and their quality;
  • the forum in which the assessment is made.

Whatever the method, the Protocol says the result has to make sense when it is set against what happened on site. A report should say which method was used, why, and what its limits are.

The records the analysis needs

  • The baseline programme and every revision, in the software’s own file format.
  • The programme updates issued during the job.
  • Progress reports, site diaries and daily and weekly records.
  • Meeting minutes, correspondence and notices.
  • Drawing, information request and approval logs.
  • As-built dates and dated photographs.

The records decide which methods are open. It is better to know that before a delay case is committed to paper, which is why a delay expert is best appointed early.

What the tribunal receives

A written report that sets out the instructions, the programmes and documents relied on, the method and the reasons for it, the critical path through the job, the delay found in each period, and every assumption and gap in the records. Whether an event entitles a party to time or money under the contract is for the tribunal. More on the role is on our delay expert witness page.

Related experience

DelayCross-examined by KC

Hospital

Region
UAE
Forum
DIAC arbitration
Parties
Owner v main contractor
Our role

Delay expert

Issues

Responsibility for delay

Evidence

Expert reports, joint statements; oral evidence under cross-examination by King’s Counsel

Experts: Jamie Shafto
DelayCross-examined

International airport

Region
Gulf
Forum
ICC arbitration
Parties
Main contractor v specialist systems subcontractor
Our role

Delay expert

Issues

Responsibility for delay

Evidence

Expert reports, joint statements; oral evidence under cross-examination

Experts: Jamie Shafto
DelayCross-examined

Solar power plant

Region
Middle East
Forum
ICC arbitration
Parties
EPC contractor v civil subcontractor
Our role

Delay expert

Issues

Responsibility for delay

Evidence

Expert reports, joint statements; oral evidence under cross-examination

Experts: Jamie Shafto
Delay

Crude oil refinery

Region
Gulf
Forum
Two arbitrations (ICC and DIAC)
Parties
EPC contractor v subcontractors
Our role

Delay expert

Issues

Responsibility for delay

Evidence

Independent delay analysis and expert reports

Experts: Jamie Shafto

Questions and answers

What is forensic delay analysis?

An analysis, carried out after the event, of what delayed completion of a construction project and by how long. It is built from the programmes and progress records the project produced and is used as evidence in claims and disputes about time.

What are the methods of delay analysis?

The Society of Construction Law Delay and Disruption Protocol describes six in common use: impacted as-planned, time impact analysis, time slice windows, as-planned versus as-built windows, retrospective longest path and collapsed as-built.

Which method of delay analysis is best?

No method is right for every dispute. For analysis after the event, the second edition of the Protocol does not prefer one. The choice depends on the contract, the events, the records and programmes available, the time available, the forum and what is proportionate.

What is the SCL Delay and Disruption Protocol?

Guidance on delay and disruption published by the Society of Construction Law. The second edition was published in February 2017. It is not a contract document or a statement of the law, and it gives way to the contract and the governing law.

Can delay be analysed without a reliable baseline programme?

Sometimes. The Protocol describes methods that rely less on the baseline programme and on software, and recognises that the critical path can on occasion be established from a practical analysis of the facts or from production and resource data. What can be done depends on the records.

Who carries out forensic delay analysis at Davies Kelly?

Jamie Shafto, founding partner and testifying delay expert. He has been appointed in ICC and DIAC arbitrations and has given oral evidence under cross-examination by King’s Counsel.