Prolongation costs

Prolongation costs are the time-related costs of being on a project for longer than planned: site staff, accommodation, plant, insurances and the like. Valuing them is the quantum expert’s work, and it rests on the delay expert’s finding of which periods of delay count.

What prolongation costs are

Some costs depend on how long a contractor is on site, not on how much work is done. Site management and supervision, offices and welfare, standing plant, scaffolding, security, insurances and bonds all run by the week or the month. When completion is delayed, these costs run for longer. The extra is the prolongation cost.

What a claim has to show

  • That completion was delayed, and for how long. This comes from the delay analysis.
  • That the delay was caused by an event for which the contract gives the contractor money as well as time. Not every extension of time carries money.
  • That the costs claimed were actually incurred, and are time-related.
  • That none of the cost is recovered elsewhere, for example in the rates for varied work.

How prolongation is valued: the Protocol

The Society of Construction Law Delay and Disruption Protocol (2nd edition, February 2017) sets out principles on compensation for prolongation. In summary:

  • Unless the contract provides otherwise, compensation is based on the actual additional cost the contractor incurred.
  • The cost is taken from the period in which the effect of the event was felt, not from the extra period at the end of the job.
  • Tender allowances have limited relevance to what the delay actually cost.
  • Where the employer’s delay and the contractor’s own delay are concurrent, the contractor should recover only the extra cost it can show was caused by the employer’s delay.

The contract comes first. Some contracts fix how time-related cost is to be valued, and the valuation then follows the contract.

The Protocol is published guidance, not a contract document and not a statement of the law. It was written with English law in mind and gives way to the contract and the governing law. Where this page says what the Protocol recommends, that is a summary of the Protocol, not an opinion on any dispute.

Head office overheads

A delayed project can also tie up the contractor’s head office. The Protocol separates dedicated overheads, the head office cost that can be shown from records to have been spent on the delay, from unabsorbed overheads, the general cost of running the business that the delayed project could not contribute to because its resources were held up. For unabsorbed overheads, the Protocol says the contractor has to show that other paying work was available and could not be taken on. Formulae such as Emden and Eichleay are, in the Protocol’s words, to be used with caution, and it does not support the Hudson formula. Whether overheads and profit are recoverable at all is a matter of the contract and the governing law.

The records we ask for

  • Cost ledgers and the accounts for the project.
  • Payroll and staff allocation records.
  • Plant records, hire invoices and site accommodation costs.
  • Insurance and bond charges.
  • The tender build-up of preliminaries.
  • The delay analysis, which fixes the periods to be valued.

Quantum and delay together

The quantum expert takes the periods of delay from the delay expert and values them, so the two reports have to fit. We can provide both from one firm, each expert responsible for their own report, or work alongside a delay expert from another firm.

Related experience

QuantumDelay

Phosphate processing facilities

Region
North Africa
Forum
Pre-arbitral expert procedure (ICC expert determination), then arbitration
Parties
Employer, contractor, subcontractor
Our role

Lead quantum expert; delay expert advice; quantum analysis

Issues

Prolongation, disruption and productivity loss, head office overheads, variations, subcontractor claims

Evidence

Written and oral testimony in the expert procedure; the arbitration settled before the hearing

DelayQuantumCross-examined by KC

LPG extraction and fractionation plant

Region
Gulf
Forum
ICC arbitration
Parties
EPC contractor v subcontractor (two subcontracts)
Our role

Delay expert; quantum expert for the main contractor

Issues

Responsibility for delay, prolongation, disruption, variations, head office overheads

Evidence

Oral evidence under cross-examination by King’s Counsel (delay)

Quantum

Slaughterhouse and associated infrastructure

Region
Gulf
Forum
Arbitration
Parties
Main contractor v employer
Our role

Quantum expert; quantum analysis support

Issues

Prolongation, disruption, variations, head office overheads, late payment

Evidence

Expert report

Questions and answers

What are prolongation costs?

The time-related costs a contractor incurs because it is on a project for longer than planned, such as site staff, site accommodation, standing plant, insurances and bonds.

How are prolongation costs calculated?

The contract comes first. Where it does not say otherwise, the Society of Construction Law Protocol’s guidance is that prolongation is valued at the actual additional cost incurred, taken from the period when the effect of the delay was felt.

Does an extension of time give a right to prolongation costs?

Not automatically. Time and money are separate entitlements under most contracts. Some events carry time only.

Can the tender preliminaries be used to value prolongation?

The Protocol says tender allowances have limited relevance, because the question is what the delay actually cost. Some contracts do provide for valuation at agreed rates, and then the contract governs.

Can head office overheads be claimed for a delayed project?

That depends on the contract and the governing law. Where they can be, the Protocol separates dedicated overheads, shown from records, from unabsorbed overheads, and says that formulae such as Emden and Eichleay should be used with caution.

What records are needed to prove prolongation costs?

Cost ledgers, payroll and staff allocation records, plant and site accommodation costs, insurance and bond charges, and a delay analysis that fixes the periods of delay to be valued.