Payment disputes on construction projects

When a contractor or subcontractor has not been paid, two questions come before any other: how much is properly due under the contract, and can the records prove it? We answer those questions, as advisers before a dispute and as independent experts once one has started.

Why payment stops

  • Work that was carried out but has not been certified.
  • Variations that were instructed and built but never valued or agreed.
  • Deductions and contra charges made without a build-up.
  • Delay damages set against the sums due.
  • Retention that has not been released.
  • A final account that has not been agreed.
  • A subcontract that makes payment depend on the main contractor being paid first.
  • Termination, with the account left open.

Working out what is owed

The sum owed is not the figure on the last unpaid invoice. It is the value of the work done under the contract, plus the value of the changes and any claims the contract allows, less what the other party is entitled to deduct, less what has been paid.

Each of those parts can be disputed, and each has to be proved from the project’s own records. A claim for unpaid money that deals with only one of them is easy to answer with a counterclaim on another.

Back-to-back and pay when paid terms

Many subcontracts in the Gulf are written back-to-back with the main contract, and some say the subcontractor is paid only when the main contractor has been paid. Whether a term of that kind can be relied on in your case is a legal question for your lawyers. The valuation question stays the same either way: what is the subcontract work worth, and what has been paid for it? A subcontract account that lines up, item by item, with the main contract account is far harder to dispute.

What we do

  • Independent review. A frank second opinion on what the account is worth and how well the records support it, before you spend on pursuing it.
  • Claim preparation. Setting out the unpaid account, the variations and the claims, each tied to the contract and the records.
  • Expert evidence. If the dispute goes to arbitration, an independent quantum opinion for the tribunal.

The first two are advisory work, done in the client’s interest. The third is independent. We do not act as testifying expert in a dispute in which we have advised the same party, unless that has been disclosed and the tribunal and the parties have had the chance to object.

We are not lawyers and we do not collect debts. Where legal advice is needed, we work alongside the lawyers you appoint.

The records to gather

  • The contract or subcontract, with its payment and valuation terms.
  • Payment applications, certificates and invoices, and a record of what has been paid.
  • Variation instructions, quotations and site measurement records.
  • Notices and correspondence on deductions and on late payment.
  • The programme and progress records, if delay is in issue.
  • The final account, if one has been submitted.

The first step

Tell us who the parties are, so that we can check for conflicts before anything else. A short call then covers the contract, the sums in issue and the timetable. Scope and fees are agreed in writing before any work starts, and we ask that no confidential documents are sent until then. You can start from our contact page.

Related experience

DelayQuantum

Landmark hotel

Region
UAE
Forum
DIAC arbitration
Parties
Subcontractor v main contractor (MEP packages)
Our role

Delay expert; quantum expert; quantum analysis support

Issues

Responsibility for delay; variations, prolongation and disruption across MEP packages; alleged scope creep

Evidence

Expert reports and a joint statement

Quantum

Slaughterhouse and associated infrastructure

Region
Gulf
Forum
Arbitration
Parties
Main contractor v employer
Our role

Quantum expert; quantum analysis support

Issues

Prolongation, disruption, variations, head office overheads, late payment

Evidence

Expert report

Questions and answers

I have not been paid on a construction project in Dubai. Where do I start?

With the contract and the records. Establish what is due under the contract: the value of the work, the variations and any claims, less proper deductions and the sums already paid. An independent review of that account shows what the records support before you commit to pursuing it.

Do I need a lawyer, a claims consultant or an expert witness?

They do different things. A lawyer advises on your rights and runs the proceedings. A claims consultant prepares or defends the claim in your interest. An expert witness gives an independent opinion to the tribunal on what the claim is worth. Many payment disputes need the first two early and the third only if the dispute goes to arbitration.

Can you tell me whether an unpaid claim is worth pursuing?

Yes. An independent claim review gives a frank view of what the account is worth and where the records are weak. Whether you have a legal right to the money is a question for your lawyers.

The main contractor says it will pay when it is paid. Is that the end of it?

Not necessarily. Whether a pay when paid term can be relied on depends on the subcontract and the governing law, and is a question for your lawyers. It does not change what the work is worth, and a properly valued account is needed whichever way that question is answered.

Do you act for subcontractors as well as main contractors?

Yes. Our experience includes a DIAC arbitration between an MEP subcontractor and a main contractor on a landmark hotel in the UAE, on variations, prolongation and disruption across the MEP packages.

What does it cost to have a claim reviewed?

It depends on the size of the account and the state of the records. Scope and fees are agreed in writing before any work starts.