Termination of a construction contract

When a construction contract is terminated, the legal argument is about whether the termination was valid. The money argument is about the account: what the work was worth on the day it stopped, and what each party can claim from the other.

What has to be valued

  • The work carried out up to the date of termination.
  • Materials and goods on site, and those ordered or made but not delivered.
  • Plant, temporary works and site facilities left behind or taken over.
  • The cost of completing the works with another contractor.
  • Delay damages and the cost of putting defects right.
  • The contractor’s costs of leaving site, and any loss the contract or the law allows it to claim.

Which items apply

That depends on who terminated, on what ground, and on what the contract and the governing law say follows. Those are questions for your lawyers and, in the end, for the tribunal. Because the outcome is often not known until the award, the quantum evidence usually has to value the account on more than one basis: as if the termination was valid, and as if it was not.

The cost to complete

An employer’s claim for the extra cost of completing the works is tested in the same way each time.

  • Is the completion scope the same as the scope of the original contract, or has work been added or improved?
  • Were the completion contractor’s prices reasonable, and how was that contractor chosen?
  • Is the same item also claimed as a defect or as delay damages?
  • What would it have cost to complete under the original contract?

Records to secure straight away

The state of the works on the day of termination is the foundation of every later valuation, and it is quickly lost.

  • A dated photographic and, where possible, a measured record of the works.
  • An inventory of materials, plant and temporary works on site.
  • The latest programme update and progress report.
  • The last payment application and certificate, and a record of payments.
  • The status of each subcontract and supply order.
  • The notices and correspondence leading up to the termination.

What our experts do

The quantum expert values the work done and the claims each way. Where it matters how far the works had progressed or how late they were, a delay expert establishes that from the programmes and progress records. Where defects are alleged, a technical expert gives an opinion on their cause and on what is needed to put them right. More is on our expert witness services page.

Questions and answers

What is a contractor paid when a construction contract is terminated?

It depends on the contract, the ground of termination and the governing law. The starting point is usually the value of the work done up to the date of termination. What is added to it or deducted from it is a legal question, and a quantum expert values each item.

What can an employer claim after terminating a contractor?

Commonly the extra cost of completing the works, delay damages and the cost of putting defects right, where the contract and the law allow. Each has to be proved, and the completion cost has to be for the same scope as the original contract.

How is the work valued at the date of termination?

From the contract rates and prices and from the records of what had been built: measurements, progress reports, photographs and the last payment certificate. A record of the works made on the day of termination is the best evidence.

Does the quantum expert decide whether the termination was valid?

No. That is for the tribunal. The expert values the account on each basis the tribunal may find, so that it has a figure whichever way it decides.

What should be done on site on the day of termination?

Record the state of the works with dated photographs and, where possible, measurements, and list the materials, plant and temporary works on site. Your lawyers will advise on notices and on access to the site.