Variation claims

A variation is a change to the works the contract describes: work added, omitted or altered. Variations are the most common source of disagreement in a construction account, and on many projects they are the largest part of the sum in dispute.

The three questions in a variation dispute

  • Was it a change at all? The employer may say the work was always within the contract scope. The answer lies in the drawings, the specification and the scope documents as they stood when the contract was signed.
  • Was it properly instructed and notified? Most contracts say who may instruct a change and what notices the contractor has to give. What follows where those steps were missed is a legal question.
  • What is it worth? This is the valuation question, and it is where a quantum expert’s evidence is needed.

How a variation is valued

The contract sets the rules. Most standard forms follow a similar order: the rates and prices in the contract where the varied work is of the same kind and carried out in similar conditions; rates built up from the contract rates where it is not; and a fair valuation, usually reasonable cost with an allowance for profit, where the contract rates give no proper basis. Some work is valued as dayworks, from records of the labour, plant and materials used.

Under the FIDIC Red Book 1999, for example, variations are instructed under Clause 13 and valued under Clause 12. A bespoke contract may set different rules, and the valuation has to follow the contract in front of the tribunal.

Where variation claims go wrong

  • No link between the instruction, the drawing revision and the work measured.
  • A lump sum quoted with no build-up.
  • New rates claimed where the contract rates apply, or contract rates applied where the work was plainly different.
  • Omissions and credits left out of the account.
  • The same cost claimed twice, once in a variation and again in a claim for delay or disruption.
  • The effect of many changes on time and productivity claimed inside the variations, with no separate analysis.

Many variations at once

A large number of changes can slow a project and reduce productivity beyond the direct cost of each change. That effect is not a variation in itself. It has to be shown as delay or as disruption, with its own evidence. Our pages on extension of time claims and disruption claims cover how.

The records we ask for

  • The contract, its valuation rules and the bills of quantities or schedules of rates.
  • The tender drawings and specification, and every later revision.
  • Instructions, requests for information and the replies to them.
  • Variation quotations, with their build-ups.
  • Site measurement records, daywork sheets and photographs.
  • Cost records for work valued on cost.

What a quantum expert does

Values each variation independently, on the contract’s rules and the project’s records. Where the parties disagree on whether an item is a change, that is for the tribunal, and the report gives a figure on each side’s case so that the tribunal has an answer whichever way it decides. More on the role is on our quantum expert witness page.

Related experience

QuantumDelay

Phosphate processing facilities

Region
North Africa
Forum
Pre-arbitral expert procedure (ICC expert determination), then arbitration
Parties
Employer, contractor, subcontractor
Our role

Lead quantum expert; delay expert advice; quantum analysis

Issues

Prolongation, disruption and productivity loss, head office overheads, variations, subcontractor claims

Evidence

Written and oral testimony in the expert procedure; the arbitration settled before the hearing

DelayQuantumCross-examined by KC

LPG extraction and fractionation plant

Region
Gulf
Forum
ICC arbitration
Parties
EPC contractor v subcontractor (two subcontracts)
Our role

Delay expert; quantum expert for the main contractor

Issues

Responsibility for delay, prolongation, disruption, variations, head office overheads

Evidence

Oral evidence under cross-examination by King’s Counsel (delay)

DelayQuantum

Landmark hotel

Region
UAE
Forum
DIAC arbitration
Parties
Subcontractor v main contractor (MEP packages)
Our role

Delay expert; quantum expert; quantum analysis support

Issues

Responsibility for delay; variations, prolongation and disruption across MEP packages; alleged scope creep

Evidence

Expert reports and a joint statement

Questions and answers

What is a variation in a construction contract?

A change to the works the contract describes: work added, omitted or altered, usually on the instruction of the employer or the engineer.

How is a variation valued?

On the rules in the contract. Most standard forms use the contract rates where the varied work is similar, rates built up from them where it is not, and a fair valuation where the contract rates give no proper basis. Some work is valued as dayworks.

Can a contractor be paid for a variation that was never instructed in writing?

That depends on the contract and the governing law, and is a question for your lawyers. A quantum expert can value the work on the assumption that it is a variation, and on the assumption that it is not.

What records prove a variation?

The instruction or the drawing revision that changed the work, the contract documents that show the original scope, and the measurement or cost records that show what was built.

Can the delay caused by variations be claimed as part of the variation?

Usually it has to be shown separately. The time effect is a matter for an extension of time claim and the loss of productivity for a disruption claim, each with its own evidence, and care is needed that no cost is counted twice.

Who values variations at Davies Kelly?

Our quantum team, led by Michael Roos, founding partner and testifying quantum expert.

Discuss your matter