Construction claims consultants in Dubai

Davies Kelly is a Dubai firm of quantum, delay and technical specialists. Most of our work is independent expert evidence in arbitration. The same people also work as claims consultants: we prepare, review and defend construction claims for contractors, subcontractors and employers across the UAE and the wider Gulf.

What a claims consultant does

A claims consultant works for you. The job is to set out what you are entitled to under the contract, in time and in money, and to prove it from the project’s own records, or to test and answer a claim made against you.

That is different from an expert witness, who gives an independent opinion to a tribunal. We do both, and we tell you at the outset which role we are in. The difference is explained on our page on claims consultants and expert witnesses.

Reviewing a claim before you commit to it

Before a claim is submitted, or before a decision to go to arbitration, an independent review shows where the claim is strong, where it is weak and which records are missing. We have advised a client that only a fraction of a claim valued by another consultancy was likely to be recovered. More on our claim review and advisory page.

Defending a claim

For employers and main contractors who receive a claim, we test it against the contract and the records: whether the event happened, whether the contract gives time or money for it, whether the delay analysis holds, and whether each sum was incurred and is valued as the contract requires. More on our page for employers, developers and owners.

How we work

  • From the contract. We start with what the contract says about notices, time, valuation and payment.
  • From the records. Programmes, progress records, instructions, cost ledgers and correspondence. A claim is only as good as the records behind it.
  • On the issues that matter most. We focus on the events with the greatest effect on time and money.
  • With a frank view. If part of a claim is not supported, we say so before the other side does.

Experience

  • For a main contractor in the UAE, a consolidated extension of time and cost claim built from first principles and managed through to the engineer’s determination.
  • Consolidated extension of time claims for EPC contractors on power and LPG infrastructure in the UAE.
  • An interim disruption claim valued by measured mile for a contractor on gas export pipelines in Saudi Arabia.

If the dispute goes to arbitration

A claim that is prepared properly is easier to settle. If it does not settle, the tribunal will usually want independent expert evidence on delay and on quantum.

We do not act as testifying expert in a dispute in which we have advised the same party, unless that has been disclosed and the tribunal and the parties have had the chance to object.

We agree at the outset who does the advisory work, so that the choice of expert is still open later. More on our independence page.

Fees and first steps

We check for conflicts first, then agree the scope and the fee in writing before any work starts. Work with a defined scope, such as a claim review, can be done for a fixed fee. More on fees and first steps.

Related experience

DelayQuantumCross-examined by KC

LPG extraction and fractionation plant

Region
Gulf
Forum
ICC arbitration
Parties
EPC contractor v subcontractor (two subcontracts)
Our role

Delay expert; quantum expert for the main contractor

Issues

Responsibility for delay, prolongation, disruption, variations, head office overheads

Evidence

Oral evidence under cross-examination by King’s Counsel (delay)

DelayQuantum

Landmark hotel

Region
UAE
Forum
DIAC arbitration
Parties
Subcontractor v main contractor (MEP packages)
Our role

Delay expert; quantum expert; quantum analysis support

Issues

Responsibility for delay; variations, prolongation and disruption across MEP packages; alleged scope creep

Evidence

Expert reports and a joint statement

Quantum

Slaughterhouse and associated infrastructure

Region
Gulf
Forum
Arbitration
Parties
Main contractor v employer
Our role

Quantum expert; quantum analysis support

Issues

Prolongation, disruption, variations, head office overheads, late payment

Evidence

Expert report

Questions and answers

Who are the construction claims consultants in Dubai?

Davies Kelly is a Dubai firm of quantum, delay and technical specialists. We prepare, review and defend construction claims for contractors, subcontractors and employers, and we give independent expert evidence in arbitration.

What does a construction claims consultant do?

A claims consultant sets out what a party is entitled to under the contract, in time and money, and proves it from the project records, or tests and answers a claim made against that party. The consultant works in the client’s interest.

What types of claim do you prepare?

Extension of time, prolongation costs, disruption and loss of productivity, variations, final accounts, unpaid work and the account after a termination.

Do you act for subcontractors?

Yes. We act for employers, main contractors and subcontractors. Our experience includes a DIAC arbitration between an MEP subcontractor and a main contractor on a landmark hotel in the UAE.

If you prepare our claim, can you also be our expert witness?

We do not act as testifying expert in a dispute in which we have advised the same party, unless that has been disclosed and the tribunal and the parties have had the chance to object.

Do you work outside Dubai?

Yes. We are based in Dubai and work on projects across the UAE, including Abu Dhabi, and in Saudi Arabia, Qatar and Oman.

How much does it cost to have a claim prepared or reviewed?

It depends on the number of issues, the size of the account and the state of the records. The scope and the fee are agreed in writing before any work starts, and work with a defined scope can be done for a fixed fee.

Discuss your matter