The four questions a quantum expert asks of every claim

A construction claim can run to hundreds of items. An independent quantum expert puts each one through the same four questions, and says plainly where a figure does not pass.

1. Was the cost or loss actually incurred?

The starting point is the project’s own records: cost ledgers, payroll, labour allocation sheets, plant records, subcontract accounts and invoices. A figure taken from a tender rate, an estimate or a spreadsheet prepared for the claim is not evidence that the money was spent. The expert checks a sample of the entries back to source documents, confirms the costs belong to the project and the period claimed, and says where the records are missing and what cannot be supported without them. Where the contract values an item at rates and not at cost, the rate still has to be shown to be the one the contract provides.

2. Was it caused by the event relied on?

A cost can be real and still not belong to the claim. The expert looks for the link between the event and the cost: which resources were affected, in which period, and what they would have been doing otherwise. For time-related costs that link comes from the delay analysis, so the quantum expert takes the periods of delay from the delay expert. The cost of a delay is generally valued in the period when the delay happened, which may not be the same as the cost of the extra weeks at the end of the job, although this depends on the facts. A claim that compares total cost with total payment and puts the difference down to a list of events leaves the link to inference. Tribunals accept that only in limited circumstances, and it carries known risks.

3. Is it valued the way the contract requires?

The contract usually says how a variation or an extra cost is to be valued: at contract rates, at rates derived from them, at fair rates, or at cost. It may also set notice requirements, caps and exclusions. The expert applies the contract’s valuation rules to each item. What the contract means where the parties disagree is a legal question for their lawyers and the tribunal. The expert does not interpret the contract, and states the reading on which each figure is based.

4. Has any of it been counted twice?

Overlap is common in large claims. The same supervisor can appear in the prolongation claim and in the preliminaries of a variation. Lost productivity can be claimed as disruption and again inside acceleration costs. Head office overheads can be recovered through a formula and also through a percentage added to variations. A cost can also be claimed as extra when the original contract price already allowed for it. The expert checks each head of claim against the others and against the contract price, and removes the overlap.

What this means before a claim is pleaded

The four questions can be asked of a draft claim as easily as a pleaded one. Asked early, they show which figures the records support and which need more evidence while there is still time to find it. The expert does not decide who is liable. The expert values the cost effect of the events relied on and states the facts and assumptions each figure rests on, so that the tribunal can see what the figure depends on.

Questions and answers

What are the four questions a quantum expert asks of a claim?

Was the cost or loss actually incurred? Was it caused by the event relied on? Is it valued the way the contract requires? Has any of it been counted twice?

Does a quantum expert interpret the contract?

No. What the contract means where the parties disagree is a legal question for their lawyers and the tribunal. The expert does not interpret the contract, and states the reading on which each figure is based.

Does a quantum expert decide who is liable?

No. The expert values the cost effect of the events relied on and states the facts and assumptions each figure rests on, so that the tribunal can see what the figure depends on.

Discuss your matter